ntpc price escalation formula |
#2
| |||
| |||
Re: ntpc price escalation formula
I was beginning to submit price escalation for supply part for one of the NTPC Project . The contract escalation formuale is EC = EC1 -EC0 EC1= EC0{F+a x A1/A0 X f1 + b x B1/B0 X f2 + c x C1/C0 X f3 + ....+Lb X L1/L0 x fLb) A,B,C shall be published price indices of corresponding major materials/items.Such indices shall necessarily be of the country of origin of goods . My confusion is 1) Whether I should consider A- ferrous metal index ,B- Fuel and power, C- Non ferrous metal index ? or only considering A-All commodities index B- Ferrous metal index and no Fuel and power 2)Factors to be considered for A,B,C or I should consider A,B only ?If so wot are the factors .Purpose is for supply of electromechanical items price escalation for Water Treatment Plant Package . Can anyone help please . |
|