Discuss about metro train cidco here. Welcome to Courses.ind.in and this page is for metro train cidco discussion. If you are looking for information on metro train cidco then ask your question is as much details as possible in the “Reply” box provided below. The more detailed your question will be, the more easy will it be for our experts to answers your query. And if you have any updated or latest information on metro train cidco, then please share you knowledge with our experts in the “Reply” box below. Your reply will be published here and your knowledge can help many people. Thanks for stopping by at Courses.ind.in. Please visit again.
Reply With Quote Quick reply to this message
  #2  
Old February 5th, 2018, 04:57 PM
Unregistered
Guest
 
Default Re: metro train cidco

Hello sir, is there any one can tell me which Metro Rail Corridors have been finalized by City and Industrial Development Corporation?
Reply With Quote Quick reply to this message
  #3  
Old February 5th, 2018, 04:58 PM
Super Moderator
 
Join Date: Aug 2012
Default Re: metro train cidco

The CIDCO is envisaged developing metro rail corridors in Navi Mumbai in addition to the suburban rail system and bus based public transport system so as to establish better North-South and East-West connectivity between all the residential nodes and to improve connectivity with Mumbai's transportation system.

These metro trains are provides connectivity between two stations and consuming less time to reach destination.

The following FIVE Metro Rail Corridors have been finalized for development in phases by CIDCO:

Sr. No. Corridor Length Priority Implementing Authority
1 Belapur-Taloje-Pendhar-Khandeshwar-NMIA 23.40 km I CIDCO
2 Mankhurd-NMIA-Panvel 32.00 km II MMRDA
3 Sewree-Kharkopar-NMIA (MTHL) 22.00 km II MMRDA
4 Dighe-Turbhe-Belapur 20.00 km III NMMC
5 Vashi-Ghansoli-Mahape 9.00 km III NMMC
Total 106.40 km

Detail of CBD Belapur to Pendhar, train of CIDCO:

Name of the Station Interstation Distance Cumulative Remark
CBD Belapur Terminal 0.06 km 0.06 Suburban Railway connectivity
Sec-7, CBD Belapur 0.71 km 0.77
CIDCO Science park Kharghar 1.27 km 2.04
Utsav Chowk, Kharghar Through Sky walk 1.37 km 3.41 Suburban Railway connectivity
Sector 11, Kharghar 0.71 km 4.12
Sector 14, Kharghar 1.00 km 5.12
Central Park, Kharghar 1.00 km 6.12
Pethpada, Kharghar 1.32 km 7.44
Sector34, Kharghar 1.23 km 8.67
Panchanand 1.48 km 10.67 Suburban Railway connectivity
Pendhar Terminal 0.95 km 11.10
Total for Line 11.10 km 11.10 11 Stations

Progress of Different Work Packages of metro Train of CIDCO:



Progress of Different Work Packages:

Package Description of Work Scope of Work Estimated Cost(in crore)
CIVIL WORK
CA-1 Viaduct from Belapur to Kharghar Sect 14 length 4.34km 159
CA-2 Viaduct from Kharghar Sect 14 top pendhar length 4.91km 146
CA-12 Station no 1, 2, 3, 4, 5 & 6 6 Stations 160
CA-13 Station no 7, 8, 9, 10 & 11 5 Stations 132
Package Depot (Civil works + Viaduct + E and M general) 220
SYSTEM WORK
Rolling Stock, Traction & Power Supply, Signalling, Telecom & AFC, track work, Depot & Station equipment 800
Reply With Quote Quick reply to this message
Reply
Similar Threads
Thread
Metro Rail UHD
What Is CIDCO 12.5 Scheme
Cidco nmia
kum to mdu train
dmrc last metro timings
metro railway hyd jobs
how to reach bits pilani by train
aurangabad cidco
cidco gr
cidco director
cidco sindhudurg
cidco swapnapurti pdf
cidco pune
rrb chennai train timings
flats in cidco
cidco award
cidco naina fsi
fsi in cidco aurangabad
EMU DMU train time table
Delhi Metro Vaishali Metro Station


Quick Reply
Your Username: Click here to log in

Message:
Options



All times are GMT +5.5. The time now is 06:14 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.
Search Engine Friendly URLs by vBSEO 3.6.1
vBulletin Optimisation provided by vB Optimise (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.