February 10th, 2018 01:38 PM
vikash
Re: vizag ntpc

The Coal Based Power Station of NTPC (National Thermal Power Corporation Limited) located in Vishakhapatnam in Andhra Pradesh is sourced from Kalinga Block of Talcher Coal fields in Odisha.

The plant is a national asset, and power generated is shared between multiple states, as the operator is national. Power generated by units 1 and 2, making up for 1,000 MW, is dedicated to power distribution companies owned by the Government of Andhra Pradesh.

The remainder 1,000 MW, generated by units 3 and 4, is allocated to the states of Odisha, Tamil Nadu, and Karnataka. Their shares are decided arbitrarily, with unsold power being sold to Andhra Pradesh.

Vizag NTPC

The details about Coal Based Power Station of NTPC (National Thermal Power Corporation Limited) located in Vishakhapatnam, Andhra Pradesh are as follows:

Address

P.O. Simhadri-531 020, Dist. Vishakhapatnam, Andhra Pradesh

Telephone
(STD-08924, STD-Vizag-0891) – 243001

Fax
243092

Approved capacity
2000 MW

Installed Capacity
2000 MW

Location
Near Pittavanipalem Village, Dist. Vishakhapatnam, Andhra Pradesh

Coal Source
Kalinga Block of Talcher Coal fields in Orrisa

Water Source
Yeluru canal for sweet water, Sea water for CW system

Beneficiary States
Andhra Pradesh (100%)

Approved Investment
Rs.3650.79 Cr.(I Qtr.97)

Units Commissioned
Unit-I Commissioning: Feb 2002
Unit-II Commissioning: Aug 2002
Unit-III Commissioning: Mar 2011
Unit-IV Commissioning: Mar 2012

International Assistance
JBIC

Govt. approved date
24.07.1997 (Zero date 08.07.1997)

Land Availability
3384.24 acres (entire land)

Associated Transmission System
Implemented by APTRANSCO

Associated Transmission System
Implemented by APTRANSCO

Plant Configuration
4X500 MW
February 10th, 2018 01:38 PM
Unregistered
Re: vizag ntpc

Can you tell me in detail about the Coal Based Power Station of NTPC (National Thermal Power Corporation Limited) located in Vishakhapatnam, Andhra Pradesh?
December 2nd, 2015 03:45 PM
nilesh
Vizag NTPC

Discuss about vizag ntpc here. Welcome to Courses.ind.in and this page is for vizag ntpc discussion. If you are looking for information on vizag ntpc then ask your question is as much details as possible in the “Reply” box provided below. The more detailed your question will be, the more easy will it be for our experts to answers your query. And if you have any updated or latest information on vizag ntpc, then please share you knowledge with our experts in the “Reply” box below. Your reply will be published here and your knowledge can help many people. Thanks for stopping by at Courses.ind.in. Please visit again.

Posting Rules
You may post new threads
You may post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off


All times are GMT +5.5. The time now is 08:08 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.
Search Engine Friendly URLs by vBSEO 3.6.1
vBulletin Optimisation provided by vB Optimise (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.